Momerstroff II Reaches Turbine Installation Milestone

NTR is pleased to announce the successful completion of turbine installation at the Momerstroff II wind farm in France, marked by the installation of the final blade on the project’s 10th turbine. Since construction commenced in Q1 2025, more than 22,350 hours have been dedicated to progressing the project to this important stage — reflecting the commitment, expertise, and collaboration of all teams involved. The 36 MW wind project is now energised and connected to the grid and, once fully operational, is expected to generate enough clean electricity to power more than 15,000 homes. Watch the video below to see the installation of the final blade at Momerstroff II.